AGIBA

EPROM manages the operation of the 20 million cubic feet production plant at Meliha site, implementing a plan to enhance equipment efficiency and reduce production costs. This smart strategy increased production to an average of 30 million cubic feet of gas per day, along with high-value condensates, while ensuring safe, stable operations and adherence to standard specifications.

Contract Date

EPROM is implementing operation and maintenance activities at the Meliha site since 2022.

About

Location: Western Desert, Egypt
Core Business: Exploration, development, and production of oil and gas
Capacity: Produces approximately 50,000 barrels of oil per day
Products: Crude oil, natural gas, and condensates

Plant Description

EPROM operates and maintains Agiba’s natural gas processing plant at the Maliha site, which was designed to produce 20 million cubic feet of gas per day.

Key Activities

EPROM is implementing operation and management of the 20 million cubic feet production plant at Meliha site. EPROM was able to implement a plan to develop and upgrade the equipment’s efficiency, as well as a smart plan to increase production and reduce production costs, which enabled it to increase production to an average of 30 million cubic feet of gas per day, in addition to large quantities of high-value condensates, while ensuring production according to standard specifications and stable, safe operation of the plant.